New Features

This new version features better and faster navigation, and improved user interface, quicker updates, flexible asset searching, group input, group amendment and group disposal of assets.

The new reporting utility is more focused with greater sorting ability and all reports are printable.

Help is available throughout the system and will be just one click away

 

Portal Registration

The TCD Portal allows access to TCD Web applications like the Asset Register. If you have not logged in before you must first Register here and if you change your password, you will need to re-register here also
 
System Access

If you wish to use the Asset Register System within the TCD Portal, please contact Karen Higgins in the Director Of Buildings Office at Extension 3113 or through e-mail at karen.higgins@tcd.ie

 

Your Username and Password to access the Asset Register will be your TCD Network Username and Password.
 
Asset Register Login
Click here to login
 
User Types
There are three different types of users:
  • Query User: This User has full access to view the departments assets, but update privileges are denied.
  • Update User: This User has access to the same facilities as the query user, but changes (insert, delete, amend assets) are also allowed.
  • Group Update User: This User has access to the same facilities as the update user, but bulk updates and changes are also allowed.

 

Last updated: May 01 2013. | contact us | back to top |

News and Updates

Last Updated : 03-Sep-2013.

Road Works

As part of on-going maintenance works, it is planned to resurface various tarmac locations around the college in the coming weeks commencing on the 9th of September 2013.

The following areas will not be available for parking or vehicle access (pedestrian and emergency services access only) on the following dates below.

  1. Physiology to Zoology - 4 days (9th September to 12th of September)
  2. Anatomy to Chemistry - 4 days (12th September to 17th September)
  3. Chemistry - 3 days (18th September to 20th September)
  4. House 27, House 11 to 14 - 6 days (20th September to 27th September)
  5. House 15 to 20 - 4 days  (23rd September to 27th September)
  6. Catex - 2 days (30th September to 1st October)

Please click here to see a map of the areas

 

Landscaping Works

Work is scheduled to commence on the removal of the Botany Hut and the Computer Hut to facilitate landscaping works.  These single storey pre-fabricated type buildings are located to the east of the rugby pitch and on the site bounded on the north by the Botany Building and on the south by the Fitzgerald Building (Physics).  A security fence will be erected around the huts commencing Wednesday 28th August 2013.  Please click here for a site map showing the location  of the works.  

Parking spaces to the north of the Botany Hut will be removed from Tuesday evening 27th August 2013.  Access will be maintained to all adjacent buildings including the Fitzgerald Building, Botany Building and SNIAMS.  Some short term temporary pedestrian diversions may be necessary during the works which will be signposted.

.

Traffic Restrictions

Renovations to Houses 38 and 40 on the east side of New Square will commence on Monday July 22nd 2013 with a completion date in February 2014.  This will necessitate certain changes in parking, vehicular and pedestrian routes in New Square.

  • Parking Restrictions

From 22nd July, 2013 parking will not be available on the east side of New Square or in front of Houses 38 to 40

  • Pedestrian Routes

For safety reasons during the works the path on the western side of New Square (behind the Rubrics) will be restricted to pedestrian and bicycle traffic only.  Pedestrians will also be directed to use the walkway behind Houses 33-37 in front of Aras an Phiarsaigh

  • Vehicular Traffic

A contractor’s compound will be erected to the front of Houses 38 and 40 and a single one way lane for traffic (from north to south) will operate on the east side of New Square.  A single one way lane for traffic (from east to west) will also operate along the southern side of the Square.  A  ‘two way’ traffic flow will operate as normal on the north side of New Square.  Permit holders looking for parking should note the map on the link below which shows the temporary traffic flow arrangements for the duration of the works and vehicles should avoid passing through Front Square at all times.
        
 Please Click Here for Traffic Managment Plan 

Two other maintenance projects are also due to commence that will involve further parking restrictions as follows:

Resurfacing of the College Rugby Pitch will commence from Friday July 19th, 2013 with an expected completion date of 30th September, 2013.  13 car parking spaces to the rear of House 38
will be removed for the duration of these works.   

Refurbishment works in Houses 47 to 48, will commence from Monday August 5th 2013 to August 31st  2013.  3 car parking spaces in this area will be unavailable for the duration of the works.

Any inconvenience caused by these works is regretted.

 

Fire Safety

Guide to Corridor Furniture and Equipment on Escape Routes

 


 